Construction, architectural, static, piping, mechanical equipment installation, electrical projects are prepared in accordance with customer requirements and technical specifications. |
![]() |
Once the projects have been approved, construction works begin in accordance with static and architectural projects. |
![]() |
Mechanical equipments such as pump, butterfly valve, plate exchanger, filter and installation of piping works begin. |
![]() |
Instruments such as flow meter, temperature, pressure, level are assembled. |
![]() |
Installation of MCC, PLC, Compensation panel is done. |
![]() |
Cable ties and cables are installed between the panel room and the field equipments. |
![]() |
Hydrostatics of the pipelines are done after the completion of the piping works. PLC installation and automation after completing cabling works. |
While the automation works are continuing, the motors and instruments in the field are supplied with electricity and tested. |
![]() |
After all the tests are completed, the automation tests are started. |
![]() |